Does replacing the pinned solar capacity with the experiment 269 estimate improve Primary demand research default 3 on sunny daylight half-hours?

Take-home message

Replacing the pinned solar capacity with the capacity estimate of experiment 269 did not lower the score on sunny half-hours, and no group improved by more than 0.011 points. The research forecast of demand at six Primary substations (anonymised as D5, D9, D10, D11, D14, and D16) subtracts the output of unmetered rooftop solar from each substation's demand. The size of that solar (its capacity) is pinned to the values of experiment 45. Experiment 269 found that a table learned from six metered solar farms recovers 0.89 to 0.97 of the output of an injected farm, where the physical fleet shape recovers 0.78 to 0.83.

We asked whether a capacity read that way gives a better forecast. We refitted the first stage of the forecast (a convex demand model with a Kalman filter, from experiment 139) with the pinned capacity swapped for the new estimate, which was refitted each month on earlier rows only.

Scores are quantile scores in points of the substation's effective capacity, smaller is better. On the sunniest third of daylight half-hours (the third of each Primary's daylight half-hours with the highest solar output per unit of capacity), the score rose from 4.371 to 4.418, a change of +0.047 points (95% interval from resampling whole months, -0.029 to +0.135). A positive change means a worse score. The interval includes zero, so the data cannot tell. Verdict: inconclusive. The pre-registered rule asks for an interval wholly below zero, which the score did not reach.

The later stages of Primary demand research default 3 (the neural-network head, the solar summary, and the blend with the manual heuristic) and the 168 to 240 hour range were not rerun. The first stage showed no gain to carry into those stages. A gain after the first stage cannot be ruled out.

Figures

Quantile-score contrasts, 0.5 to 168 hours

Quantile-score contrasts, 24 to 168 hours

Pinned and estimated capacity by Primary

Results

  • Arms and what was refitted. The experiment changes the solar capacity inside the fitted stage and imports the default's code (a tier 2 change), and adds a plant-response table and a capacity fit per month. Arm A is the first stage with the pin (experiment 45's frozen vintage). Arm B replaces the capacity with the experiment 269 estimate, refitted at each of 27 monthly origins (2024-04 to 2026-06) on rows before the origin. Arm C holds arm B's value at the 2025-07-01 origin for the whole scored year. The stack's own unit solar shape is unchanged.
  • How the estimate is scaled. A fit to the real series reads too little of a solar farm's output. Each fit is therefore divided by the median recovery of five farms injected at that origin into the same Primary's demand, each read with the shape of the other five farms.
  • Row set and range. fold_a_daily_gap_v1, scored year 2025-07-02 to 2026-06-30, six Primaries, rows outside the hand-filtered events, forecast origin 09:00 UTC, lead 0.5 to 168 hours and 24 to 168 hours. The 168 to 240 hour range needs the experiment 317 chain, which was not rerun, so the result covers 7 of the 10 forecast days that NGED (the distribution network operator) cares about.
  • Headline, sunniest third of daylight half-hours (B minus A, scored year). At 0.5 to 168 hours: +0.047 (-0.029 to +0.135). At 24 to 168 hours: +0.044 (-0.037 to +0.133). Error of the mean forecast on the same rows, 0.5 to 168 hours: +0.120 (-0.002 to +0.277).
  • Absolute scores, sunniest third, 0.5 to 168 hours: A 4.371, B 4.418, C 4.448 (24 to 168 hours: 4.511, 4.555, 4.583). All half-hours: A 2.773, B 2.777, C 2.784. C minus A is +0.077 (-0.012 to +0.158) and C minus B is +0.030 (-0.004 to +0.076).
  • Replicate year (2024-07 to 2025-06), sunniest third, B minus A. At 0.5 to 168 hours +0.040 (-0.004 to +0.084). At 24 to 168 hours +0.044 (+0.004 to +0.085), an interval wholly above zero. Error of the mean forecast +0.106 (+0.006 to +0.187) at 0.5 to 168 hours. Both years point the same way, and the replicate year's 24 to 168 hour interval excludes zero. Arms B and C are identical in the replicate year, because both read the 2025-07-01 origin or an earlier one.
  • The other groups, B minus A at 0.5 to 168 hours: no group other than the sunniest third moved by more than 0.011 points, as the table shows.
Group Change in score 95% interval
All half-hours +0.004 -0.006 to +0.012
All daylight +0.001 -0.020 to +0.020
Darkest third of daylight -0.011 -0.025 to +0.006
Night +0.006 -0.001 to +0.015
Winter nights (December to February, after dark) -0.007 -0.010 to 0.000
  • By Primary, sunniest third, B minus A (checks.log): D5 -0.023, D10 +0.155, D11 +0.037, D14 -0.046, D9 -0.063, D16 +0.218. Leaving one Primary out gives +0.013 (without D16) to +0.070 (without D9), so the sign holds. On all half-hours, leaving out D16 gives -0.006 (-0.014 to 0.000) against +0.004 with it, so D16 carries the all-half-hours result.
  • Capacities (figure 3; ratios of the estimate to the pin for the latest season-year). At the start of the scored year (2025-07-01) the estimate is 28% below the pin at D16 (30.9 against 43.2 points of effective capacity), 15% below at D9, and 17% above at D14. By 2026-06 the pin has risen above the estimate at D11 (0.79), D14 (0.83), and D16 (0.74), and the estimate is 8 to 10% below at D5 and D9. D10 matches the pin (1.00). D9's first monthly folds keep the pin, because D9 has too little history for an estimate there (1,513 path weeks took the pin in the fit log, about four folds).
  • Tails, six Primaries, 0.5 to 168 hours (A, B, C). Coverage below q01 is 2.20%, 2.17%, and 2.18%; below q05 6.68%, 6.67%, and 6.73%; below q95 94.74%, 94.68%, and 94.67%; below q99 98.35%, 98.30%, and 98.30%. Pinball loss at q01 is 0.215, 0.216, and 0.216; at q05 0.721, 0.725, and 0.727; at q95 0.720, 0.715, and 0.716; at q99 0.220, 0.220, and 0.220. No tail moves by more than 0.006 points.
  • Reference rows. The first stage alone is not Primary demand research default 3, so it is not placed against the manual heuristic or climatology. The research default's own scores (2.727 at 0.5 to 240 hours, against 3.414 for the manual heuristic and 3.664 for climatology) are in the research default log.
  • Model family. The experiment evaluates one model family and no blend.

Checks

  • Wiring gate. Arm A equals experiment 139's stored pin forecasts at all six Primaries (95,939 to 97,046 rows each, largest gap in q01, q50, and q99 0.0; logs/checks.log).
  • Median minus mean forecast, per Primary and arm: 0.0 points for all three arms.
  • Mean-forecast error beside each contrast: it moves in the same direction as the quantile score on the sunniest third (+0.120) and on winter nights (-0.019).
  • Triggers. None fired. B's point estimate on the sunniest third (+0.047) is just outside the pre-registered band (within 0.03 points either way), but its interval covers the band and the predicted direction (no gain) held. Leaving one Primary out does not flip the sunniest-third sign.

Caveats and lab shortcuts

  • The plant-response table is not as-of. It is fitted once on the six farms' history to 2026-06-30, and the farms' scale (their 99th percentile of output) uses all daylight half-hours. Only the capacity fit, the pin, and the injection recoveries stop at each origin. The capacity is as-of; the shape it is read against is not.
  • The first stage only. The neural-network head, the solar summary, the blend, and the 168 to 240 hour range need the chain of experiments 155, 160, 164, 317, 319, and 322 refitted from the new forecasts.
  • Unit shape unchanged. The estimate is applied to the stack's physical unit shape, not to the empirical shape it was fitted with.
  • No scale factor. Experiment 139's post hoc factor of 1.15 was not repeated.

What to try next

  • Apply the experiment 269 estimate with the empirical shape it was fitted with, in the first stage and in the ensemble's solar response.
  • Test a scale factor on the estimate.