Live service (AWS deployment)

Status: ✅ v0.1 shipped (July 2026, v0.1.0) on the accepted architecture; the same architecture now runs v0.2 (v0.2.0, deployed 13 August 2026) — the naive forecast is deployed and running on AWS. Epic #137 is closed. The shipped design now lives in Production Deployment — Design (the orchestration and champion-model decisions), and the step-by-step operational recipes in the live-service runbooks (promotion, AWS bring-up, day-to-day operation).

This page is not retired yet: it remains the home of the post-v0.1 work still tracked as open issues — production monitoring (#224), the access-phasing Stages 2–3 (#328, #329), infra-as-code (#326), and the MLflow-server / dev-dashboard future work (#235, #236), and the plan for NWP model upgrades (#851). The AWS-architecture decision itself is built and running; its durable decision record now lives in Production Deployment — Design, and the running-cost estimate in AWS Running Costs. It is retired in full once production monitoring lands and its design is promoted, per the ship-time triage tracked in Engineering health.

History: the inference-asset and monitoring designs were absorbed from the Dagster ML-assets plan (phases 0–6.7 complete, PRs #182–#214); its final cleanup phase lives in Engineering health.

Requirements

v0.1 (get a live forecast running on AWS):

  • Deploy the naive forecast so it runs live on AWS, 6-hourly, writing to power_forecasts (fold_id="live") — the live_forecasts asset.
  • Forecast quality does not matter yet — science improvements (baselines, XGBoost) are explicitly out of scope for this milestone.
  • Production inference must have zero dependency on MLflow at runtime — for v0.1 the champion model is baked directly into the container image at build time and loaded via a plain save/load, so there is no run ID, cache lookup, or tracking-server call on the hot path at all.
  • Support both live (current partition) and replay (historical backfill) NWP availability modes, so missed runs can be backfilled (#208).
  • Use Dagster "properly": persistent run history, one-click UI backfills of missed partitions, and the ability to launch backtests on AWS whenever the model improves.
  • Multi-user access to the Dagster UI (and, later, to the dev dashboard) (rules out single-user tracking services).
  • Portability: the entire stack must also run on a local laptop (or any cloud) via docker compose up — no AWS-specific service (EventBridge, Step Functions) may be load-bearing for scheduling or orchestration. Portability is both a development convenience and a handover requirement — see the orchestration decision.
  • AWS infrastructure with no static AWS keys (IAM roles throughout), basic alerting on task failure (SNS → email), and cost-conscious operation (~£27–40/month target).

Post-v0.1 (explicitly deferred):

  • Forecast quality/science work — baselines, XGBoost improvements.
  • The NGED-delivery schema/contract (#96) — v0.1 is "forecast running", not "delivery contract live".
  • Basic per-task failure email alerting (a failed run → SNS → email). Sentry error telemetry and the missed-check-in alarm have shipped (#63 — see Send telemetry to Sentry); the remaining piece is the thin SNS→email notification edge for individual run failures.
  • An MLflow tracking server (issue #235) and a separate development dashboard (#236), both hosted on the always-on control-plane box once it exists — see the note below.
  • Production monitoring: score live forecasts over trailing 24h/7d windows, logged to a dedicated MLflow experiment, with a manual, auditable way to retire stale experiment partitions.
  • For more plans for post-v0.1, please see the milestones (v0.2 onwards).

The live_forecasts asset

Issue: #221

Status: ✅ Implemented, alongside the promoted_model promotion asset and local 6-hourly automation (dg dev + persistent DAGSTER_HOME, part of #208). The design rationale (single-run vs. bulk mode, the live/replay asymmetry, the trained-population invariant) now lives at Production Deployment — Design: Live inference; the operational runbook — promoting a model, running the schedule, backfilling a missed slot — is Operating the live service, the permanent home this page's shipped material moves to (and, eventually, this whole page, once every section below has landed).

Production model artifacts

Issue: #222

Status: ✅ Done. The design decision (bake the champion model into the image at build time; no MLflow at runtime) and its rationale now live at Production Deployment — Design; the promotion/build/verify runbook lives at Setting up the live service on AWS.

AWS architecture

Issue: #206 (done)

Status: ✅ Built and running. The accepted option — a small EC2 control-plane box + EcsRunLauncher — runs on AWS as v0.2 (v0.2.0), the same architecture v0.1 (v0.1.0) used, unchanged; the bring-up is documented in Setting up the live service on AWS. The access-phasing Stages 2–3 and the future-work items (MLflow server, dev dashboard) remain post-v0.1.

The Level 1 ("nothing always-on") design proposed in issue #206 is rejected. Its cost case does not hold, and there are two requirements it cannot serve. The cost case rests on pricing the always-on control plane at ~£70–105/month, which is a 16 GB box big enough to run the compute. A small control-plane box costs ~£10–20/month (costed 2026-07-02). Its RDS prerequisite goes away on a single machine too (Postgres-in-Docker, or SQLite on a real local filesystem). The two requirements Level 1 does not serve:

  1. Use Dagster "properly" — persistent run history, one-click UI backfills of missed partitions, and the ability to launch backtests on AWS whenever the model improves.
  2. An always-on dev dashboard (a simple Marimo web app showing the latest forecasts) — so a dashboard must be always-on regardless.

Decision: small EC2 control-plane box + EcsRunLauncher, decided 2026-07-11. The implementation workstreams are identical under every option except the infrastructure one.

The decision was pressure-tested again in July 2026 against the fully serverless alternative — EventBridge Scheduler firing an ECS RunTask directly, with no always-on control plane — and stands. The durable rationale (portability, NGED handover, illusory cost saving, retry parity) and the accepted trade-offs (mitigated by the external missed-check-in alarm) are recorded at Production Deployment — Design: Orchestration.

Cost summary

The running-cost estimate for the accepted option — the headline ~£27–40/month, the workload model behind it, and the storage and data-transfer arithmetic — now lives at its durable home, AWS Running Costs, alongside a projected estimate for running at v2 scale (~2,500 time series). The per-option figures sit in the decision record: the rejected alternatives range from ~£12–22/month (Option A, which fails two requirements) to ~£56–86/month (Option C).

The accepted architecture — a small EC2 control-plane box running Dagster behind Tailscale, dispatching every run to an ephemeral Fargate task via EcsRunLauncher — is built and running in production. Its rationale, and the infrastructure-tier alternatives rejected in its favour (a fully serverless "nothing always-on" design, one big box running all compute, a serverless control plane with RDS, and Dagster+ Solo), are recorded as a decision history in Production Deployment — Design: infrastructure tier alternatives to the EC2 control-plane box.

Future work (post-v0.1): once an always-on control-plane box exists (the accepted option or later), it's also a natural home for an MLflow tracking server (network-reachable, persistent — replacing the local file-store) and a "development dashboard" (a Marimo app for researchers). Neither is needed to ship v0.1; revisit once the box exists — see Access phasing below for how each one's exposure rolls out once it does.

Access phasing

The sections above decide where the accepted option's pieces run; this one decides who can reach them, when. Three stages, each additive on top of the last — nothing built in an earlier stage is reworked in a later one.

The constraint driving all three stages: none of the three web UIs has any built-in authentication. Open-source dagster-webserver has no users, roles, or login (auth/RBAC is a Dagster+ feature) — anyone who can reach the port can launch and terminate runs and wipe materialisations. MLflow's tracking UI and the Marimo dashboard are equally open. So the network layer is the auth layer: "no public inbound ports" in Stage 1 and the read-only-second-webserver pattern in Stage 2 are load-bearing security decisions, not tidiness.

Stage 1 — solo, Tailscale only

This is exactly what the accepted option already describes; it's named explicitly as Stage 1 here only so Stage 2/3 below have something to say "additive on top of."

  • Daemon, full-access Dagster webserver, and the Marimo dashboard all run on the t4g.medium control-plane box, alongside MLflow once its tracking server lands (the "Future work" item just above, issue #235) — MLflow-on-the-box is not itself a new v0.1 commitment, only its access tier is decided here.
  • Security group: no public inbound ports at all. Everything is reached over Tailscale.

Stage 2 — team gets read-only Dagster access; MLflow stays private

Issue: #328

  • A second dagster-webserver --read-only process on the same box, against the same Postgres + code location — cheap: just another process, no new daemon, no new infra beyond this.
  • Caddy in front of it, handling TLS via Let's Encrypt automatically.
  • oauth2-proxy in front of the read-only webserver for Google sign-in, using --authenticated-emails-file (not --email-domain — NGED/NIA collaborators aren't on one Workspace domain).
  • Security group opens port 443 for the first time — this is the real milestone of this stage.
  • One DNS subdomain (e.g. dagster.<domain>).
  • MLflow is explicitly not exposed in this stage — it stays Tailscale-only, unchanged from Stage 1. There is no native read-only public/gated MLflow mode without either the still-experimental auth plugin or allowlisting specific endpoints at the proxy — not worth it unless there's a real need.
  • The full-access Dagster webserver, Marimo, and MLflow remain exactly as in Stage 1.
  • Lighter alternative if (and only if) the audience is a couple of OCF colleagues: skip Caddy, oauth2-proxy, DNS, and the security-group change entirely by inviting them into the tailnet instead. Tailscale already authenticates members with their Google accounts, and a Tailscale ACL can expose just the read-only webserver's port to the team while the full-access webserver stays restricted. Worth checking whether OCF already runs an organisation tailnet before building this — if so, most of the setup (and the per-user pricing question below) is already settled. Trade-offs: everyone must run the Tailscale client (fine for colleagues, wrong for browser-only NGED/NIA collaborators), and past the free tier's ~3 users Tailscale bills per user, whereas oauth2-proxy is free. So treat tailnet-sharing as a cheap Stage-1.5 for OCF-internal read access; the Caddy + oauth2-proxy build above remains the destination once anyone outside the tailnet needs the UI. The two aren't mutually exclusive: starting with tailnet-sharing and adding the proxy later loses nothing, since Stage 1.5 builds none of the pieces Stage 2's proxy needs but also breaks none of them.

Stage 3 — public Marimo dashboard, curated public data

Issue: #329

  • A separate Marimo instance, not the private one — reads only a public-safe subset of data (ideally its own S3 prefix), runs as its own ECS Fargate task/service, no ALB.
  • No CloudFront/Lambda@Edge — instead, exploit the fact that the control-plane box is already always-on and already running Caddy:
    • Caddy gets one more route, pointed at a small custom wake-proxy service (not a direct backend).
    • Wake-proxy: checks whether the Fargate task/service is running (ecs describe-services); if not, sets desired count to 1 and polls until healthy, then reverse-proxies the request through.
    • A background loop in the wake-proxy scales desired count back to 0 after an idle period (e.g. 15 min).
    • UX: don't hold the connection open for the full ~30–60s cold start — serve an immediate "warming up" holding page that polls a /ready endpoint every 2–3s, then redirects once healthy.
  • One more DNS subdomain (e.g. dashboard.<domain>), no oauth2-proxy — fully public, no login.
  • Trade-off: this couples the public dashboard's availability to the control-plane box's uptime. Compute isolation is preserved — a Marimo bug can't touch the Dagster daemon, since it's a separate task — but if the box goes down, the public dashboard becomes unreachable too, not just the private Dagster/MLflow. Accepted trade-off for solo-project simplicity over running a fourth AWS service (an ALB) just for this.
  • Rejected alternative: Marimo's WASM/Pyodide static export (zero server, hosted on S3+CloudFront). Ruled out based on direct prior experience — ~30s browser-side cold start on a similar personal project, and clunkier than a thin server-side wake mechanism.
  • Rejected alternative: the CloudFront + Lambda@Edge wake-proxy pattern (the "textbook" AWS scale-to-zero workaround). Ruled out in favour of reusing the existing box's Caddy plus a custom script — fewer AWS services (no ALB, no CloudFront distribution, no Lambda@Edge), since compute is already sitting there.

Sequencing: Stage 1 is built and run solo, by hand — not enough moving parts yet to justify infrastructure-as-code. Stage 2 (the read-only webserver, Caddy, oauth2-proxy, the security-group change) is the natural point to start writing infra-as-code, since that's when IAM roles, security groups, and multiple processes start accumulating enough to be worth codifying and reproducing — see the open Terraform-vs-CDK question in Deployment workstream 3.

Handover caveat: all three stages are designed for the phase in which OCF runs the service on OCF's AWS account. The working assumption is that, after the Network Innovation Allowance (NIA) project, NGED runs the service on its own AWS account (see Handover to NGED). OCF's access design will need to fit NGED's cloud and security standards, so OCF needs to confirm those standards with NGED early. Here the private-network layer (Tailscale) is also the authentication layer. If NGED's standards rule out Tailscale, the whole access design therefore needs an NGED-compatible replacement. The size of that replacement is a reason to confirm NGED's cloud and security standards early — not a reason to change Stages 1–3, which remain correct for the OCF-run phase.

Production monitoring

Issue: #224

Depends on the live_forecasts asset — there is nothing to monitor until live forecasts exist.

The metrics asset implements the leaderboard and ad_hoc scopes; production_monitoring is declared in EVALUATION_SCOPES but unimplemented (EvalScopeType in contracts/ml_schemas.py deliberately omits it). And with thousands of experiments planned, the cv_experiment_folds dynamic partition set grows without bound — partition keys need a retirement path that cannot lose results.

The production_monitoring evaluation scope

  • Extend EvalScopeType to Literal["leaderboard", "production_monitoring", "ad_hoc"], bringing it in sync with EVALUATION_SCOPES (EvalScopeType's own docstring already anticipates this).
  • Remove the CV-folds-only restriction in compute_metrics() (documented in its docstring): fold_id="live" rows use the same join logic, with window bounds supplied by the caller (trailing windows, not fold dates).
  • Scope behaviour in the metrics asset: score fold_id="live" forecasts over two trailing valid_time windows — last 24 hours and last 7 days. Each window writes rows to forecast_metrics Delta with window_label ("24h"/"7d"), the trailing window_start/window_end bounds, and computed_at = now (all columns already exist in the Metrics schema). window_start/window_end are part of Metrics.PRIMARY_KEY, and a trailing window is computed relative to "now", so most runs write rows the table has not seen before and the series accumulates. Metrics.validate() rejects a batch that duplicates an existing primary key, so a genuine recomputation of an existing window — a retried sensor firing, a backfill — cannot land as a second row for that key: this scope's writer has to replace the existing row instead. write_forecast_metrics does not do that today — its overwrite predicate scopes only to (experiment_name, fold_id), one partition shared by every window this scope writes, so reusing it unchanged would delete every other window's rows sharing that partition. This scope's writer needs a predicate (or another instrument) scoped to the full primary key.
  • MLflow: log the same aggregates to a dedicated production_monitoring MLflow experiment — never to the golden leaderboard — as time-series points (MLflow metric timestamp/step), one persistent run per window resolved by tag (mirroring the mlflow_runs get-or-create convention), so MLflow charts live performance over time (e.g. trailing-7d NMAE per time_series_type). Stamp mlflow_run_id on the Delta rows as the cross-link.
  • Note: evaluating "the last 24h of production" scores forecasts whose valid_time has already passed and now has observed power — satisfied naturally as observations accumulate.

The monitoring_sensor

A Dagster sensor that fires on each power_time_series_and_metadata materialisation (~every 6 h, when new actuals land) and requests a metrics run with evaluation_scope="production_monitoring" over fold_id="live" for both trailing windows. Sensor preferred over a schedule so it fires on the actual data update.

Note this sensor needs a running Dagster daemon — the accepted option provides one.

Alert on absence: the missed-check-in alarm

Status: ✅ Shipped (#63). The heartbeat, the failure hook, and the laptop/production environment split are built and documented as-built in Send telemetry to Sentry. This section keeps the why — the design rationale for alerting on absence from outside the deployment. The remaining monitoring work on this page is the separate per-task failure email edge (SNS → email).

Per-task failure alerts (Deployment workstream 3) only fire when a task runs and fails. Whole classes of failure are silent: a hung daemon, a full disk, an expired credential, a schedule that stopped firing. The primary production alert is therefore a missed-check-in alarm (Sentry's cron-monitoring terminology): it fires when no successful forecast has landed in N hours (e.g. 8 hours — one missed 6-hourly slot plus margin), regardless of cause. An alert feeding a runbook — rather than paging or automatic failover — is a proportionate response because the project's uptime requirements are lenient by design. The accepted option's "daemon silently dead" staleness alarm (described in the architecture options) is this alarm; recording it here makes it a first-class monitoring deliverable rather than a side note.

The alarm's evaluation and delivery must sit outside the service being watched, because a dead daemon cannot report itself — a Dagster sensor alone can never provide this alarm. The mechanism is Sentry cron monitoring (#63): each successful forecast run checks in with Sentry, and Sentry alerts when an expected check-in fails to arrive. This satisfies both the outside-the-service requirement and the portability preference in Deployment workstream 3 — Sentry is external to the whole deployment, and a check-in ping is plain code that works identically from a laptop, AWS, or any other cloud. One handover consideration: the Sentry account is OCF's today, so at handover the alert routing (and possibly the account itself) moves to NGED — see Handover to NGED.

Every alert must link to a runbook that ends in either a specific operator action or "escalate" — a requirement that matters doubly under the post-NIA operating model, where the day-to-day operators are NGED staff who did not develop the code, working from the runbooks (see Handover to NGED).

The retire_experiment_job

A manually triggered job (deliberate and auditable — never automatic) with a single config field experiment_name: str:

  1. Verify before deleting: the MLflow parent run exists and carries aggregate metrics, and power_forecasts Delta contains rows for this experiment_name. If either check fails, raise and delete nothing.
  2. Delete the experiment's dynamic partition keys via context.instance.delete_dynamic_partition("cv_experiment_folds", key) for each f"{experiment_name}__{fold_id}".
  3. Log the deleted keys as output metadata.

Retirement does not delete MLflow runs or Delta forecasts — those remain the permanent record; it only prunes Dagster's execution ledger. Lives beside register_experiment_job in defs/jobs.py; ops use OpExecutionContext (they need context.instance).

Interaction with the probabilistic metrics

Any metric added to compute_metrics flows through this scope automatically — once the probabilistic metrics (PICP/spread-skill) land, production monitoring tracks ensemble calibration over time for free. No coupling needed; the ordering is flexible.

NWP model upgrades

Issue: #851, under the v0.9 epic #361

Status: 🚧 Planned (v0.9). Nothing below is built. The first step is an experiment, whose result sets how long the uncertainty bands stay wide after an upgrade.

An upgrade to a weather model changes what the forecast's NWP inputs mean without making them absent or malformed, so none of the live service's checks can see it. The checks listed under Inherent Stability → Failure modes catch NWP that is missing, stale, or rejected by the Nwp contract. A run from an upgraded model arrives on time and passes validation. Upgrades are not rare: ECMWF changed the IFS cycle behind ECMWF ENS seven times between June 2019 and May 2026, and the project's ENS archive, which starts on 2024-04-01, already spans two of those changes, 49r1 on 2024-11-12 and 50r1 on 2026-05-12. The dated list, for every weather model the project reads, is Data sources → NWP model upgrades since 2019.

What the one measured upgrade showed

In the one upgrade measured so far, the beam/diffuse split study's README attributes most of the apparent loss of skill to scoring post-upgrade rows with a model trained only on pre-upgrade rows. The Met Office upgraded UKV at PS47 on 2026-01-21. The beam/diffuse split study cut its cross-validation folds as contiguous blocks of months. At five of the six generators every post-upgrade row therefore fell in the last fold, and the XGBoost model scoring that fold had trained on pre-upgrade UKV alone. Measured that way, UKV's global irradiance scored about 1 percentage point worse than ERA5's from the upgrade onwards. The weather-products study cut its folds separately before and after the upgrade, so every post-upgrade row was scored by a model that had trained on other post-upgrade months. There, XGBoost models trained on both sides of the upgrade put UKV 0.18 percentage points of capacity behind ERA5 after the upgrade [+0.05, +0.42], and XGBoost models trained on the post-upgrade months alone put UKV 0.11 points ahead [−0.21, +0.45]. The two studies score different row sets and normalise error differently, so the figures do not subtract, and the attribution rests on the README's reading rather than on a subtraction. Eight post-upgrade months cannot settle which of the two later fits is right.

The loss that remains is real for a production service, because the promoted model is always trained on the old version when an upgrade lands. Folds cut inside each era hide the loss rather than removing it: they show how good a model can be once it has trained on the new version, not how good the model already promoted is on the day the new version arrives.

Why the model is not told the NWP version

For now, XGBoost is not given the NWP model version as a feature, for two reasons. The experiment includes a post-upgrade flag as one of its setups, so the decision can be revisited on evidence.

On the day of an upgrade, no training row carries the new version, so a version feature cannot describe the new version. An ordinal version feature sends every post-upgrade row into the leaves the trees fitted to the latest version they saw. Those leaves describe the old version, which is the mismatch the feature was meant to remove. The era-covariate safety rule says the same about any era feature: an era covariate is safe only when the value production will see is well represented in training, and a new version is represented by nothing. The feature starts to help only once post-upgrade rows have built up in training, and by then a retrain, which removes the mismatch directly, does the same job. The weather-products study did give its models an era flag, but every fold's training set held post-upgrade months, which is that later case.

ECMWF upgrades its forecast model roughly once a year, so the ENS version tracks the calendar closely. The trees can use the version as a proxy for the date, and learn capacity changes, curtailment regimes, or meter swaps where they should have learned an NWP effect. The ERA5 plan is designed to avoid the same era confounding.

The plan

Record the NWP model cycle on every NWP row and every forecast row. A column naming the cycle, such as 50r1 for ECMWF ENS today, lets production monitoring split error by version. The column is filled from the dated list below, keyed on each run's init_time, so it does not depend on the feed publishing the cycle. Nwp and PowerForecast are both Patito contracts, so adding the column is a contract change, agreed before it is made. Whether the power_forecast table delivered to NGED carries the column is a question for the delivery contract (#96). The column also makes one further change possible, which is an option rather than part of the plan: cutting the canonical cross-validation folds so that a model scoring one cycle trained on that cycle, as studies.cross_validation.assign_folds already does for the studies.

Keep a dated list of upgrades in the repository, and warn when an NWP field shifts in a way the list does not explain. Each entry names the NWP model, the cycle, and the first init_time on the new cycle, and the data-sources list is where the entries come from. An upgrade the producer did not announce shows up as a sudden shift in a field's distribution that starts at one init_time and persists. A change-point test on each field's per-run statistics is the candidate detector. Choosing statistics that weather does not trip, such as the record-breaking dry, sunny July of 2026, is the open question already recorded under Input drift detection. The detector is an asset check: it warns, never blocks, and never raises. The detector's warning names the NWP model, the field, and the run where the shift starts, so a human can confirm the upgrade and add it to the list.

Treat an upgrade as a degradation, not an error. The forecast keeps running, the cycle column records that the row's NWP is post-upgrade, and the uncertainty bands widen until the promoted model has trained on enough rows from the new cycle.

Two further signals are options, not yet decided. The first is a warning row in power_forecast_warnings, which would need a new warning_type in the delivery contract. Its warning_source would name the first run on the new cycle in the table's usual form, such as "ecmwf_ens:2026-05-13T00:00Z" for 50r1, and its warning_description would name the cycle. The second is a Sentry event routed to the digest rather than to a notification, because nothing of ours has broken.

Count the promoted model's post-upgrade training in weeks of data from the row's cycle, not in days since the upgrade. A model retrained 3 weeks after an upgrade has 3 weeks of the new cycle behind it, while a model never retrained has none, however long ago the upgrade was. The same reasoning measures NWP staleness in missed runs rather than in hours. The training run records how many weeks of each cycle it saw, so serving compares the row's cycle with a number in the model's saved config, a table lookup that keeps the complexity offline. How many weeks count as enough is what the experiment measures. Widening the bands needs quantile output (#263) and regime-conditional calibration first; until both exist, the cycle column is the only signal the plan commits to.

Retrain on a schedule, and early after an upgrade. An upgrade is the concrete trigger that A retraining cadence and trigger says the project lacks. A retrain can only use post-upgrade rows whose power has been observed, so the earliest useful retrain is set by how fast those rows build up, and the experiment says how many weeks are worth waiting for. A per-series correction of the forecast, refitted on the last few weeks of observed power, might bridge the gap sooner. That correction is untested.

The experiment: how fast a model recovers after an upgrade

The experiment measures how the error on post-upgrade rows falls as training gains post-upgrade data, around the Met Office's UKV upgrade of 2026-01-21. That upgrade is the one with metered power on both sides of it in the studies' data. The recovery curve says how long the bands must stay wide after an upgrade, and whether a post-upgrade flag or recency weighting shortens that time.

The data is the weather-products study's, at the six metered solar farms. The weather input is Open-Meteo's default hourly UKV global irradiance, the column whose post-upgrade evidence conflicts, and each XGBoost model also gets the study's sun position, season, time of day, and ERA5 air temperature. One XGBoost model is fitted per generator, as in the study.

Each XGBoost model trains on every pre-upgrade row plus the first 0, 2, 4, or 8 weeks after the upgrade, under three setups:

  • No version feature, the current decision.
  • A post-upgrade flag, set to 1 on every row from the new version.
  • Recency weighting: each row's sample weight halves for every 8 weeks of age, counted back from the last training row, so the most recent 8 weeks carry half the total weight.

Every arm is scored on the same post-upgrade rows, those after the eighth post-upgrade week, so the four training lengths and the three setups are compared on one row set. At 0 weeks the flag takes a single value across the training rows, so that arm should match the no-feature arm up to fitting noise, which checks the harness. XGBoost's column subsampling stays off in every arm, because with it on, the arm holding an extra column gets a different draw of columns and the contrast measures the draw rather than the flag. A reference model trained with folds cut inside each era, as in the weather-products study, is scored on the same rows, and gives the fully recovered level the curve is heading towards.

Report each arm's absolute error, not only the contrasts between arms. Each arm gets its mean absolute error as a percentage of capacity, with a 95% interval from resampling whole months, using studies.bootstrap. Three contrasts are planned, each paired on the same rows: no version feature at 8 weeks against no version feature at 0 weeks, which says whether the model recovers at all; the flag against no version feature at 4 weeks; and recency weighting against no version feature at 4 weeks. Every other contrast is exploratory.

Two decision rules turn the result into settings. The flag or recency weighting is adopted only if its planned contrast favours it and is statistically significant at the 5% level, and its point estimate is no worse than no version feature at 2 or 8 weeks. The bands stay wide for the shortest training length whose no-feature arm's paired contrast with the reference model has an interval that includes zero. If 8 weeks does not reach that point, the duration stays open until more post-upgrade data exists.

Four limits bound how far the result carries. The scored window runs from 2026-03-18 to the end of the record, about 6 months, so whole-month resampling has few months to draw on. The 2, 4, or 8 added weeks fall between late January and mid-March, while the scored rows run from spring into summer, so the added weeks show the model little of the high-sun hours it is scored on. NGED's own correction to the power timestamps falls inside the post-upgrade window, so a change in the target can mix with the change in the input. And the input is UKV's hourly analysis, not an ECMWF ENS forecast at a lead of 3 to 10 days, so the recovery at long leads may differ. ECMWF's 50r1 upgrade of 2026-05-12 falls inside the project's ENS archive, so the same design can be repeated on the product the live service reads once enough post-upgrade months have built up.

Implementation details (deleted when this ships)

Deployment workstream 1 — the production job (local dress rehearsal)

Issue: #208 (done)

Status: ✅ Done (closed 2026-07-10). The native per-asset Dagster schedules that ship with The live_forecasts asset (power_time_series_and_metadata_schedule, ecmwf_ens_schedule, live_forecasts_schedule) do the whole job. Closing #208 took a several-day soak under dg dev with a persistent DAGSTER_HOME, which confirmed 6-hourly forecasts landing with no duplicate rows and a missed slot backfillable in replay mode. No hand-rolled freshness op is needed, and neither is the one-shot live_pipeline_job that Option A would require (Option A has no daemon to hold schedules) — Option A is rejected, so that job is not specified here.

Deployment workstream 3 — AWS infrastructure

Status: ✅ Infrastructure built and running. The Elastic Container Registry repository, the two IAM roles, the Fargate task definition, the always-on EC2 control-plane box (EcsRunLauncher, Postgres-in-Docker, schedules, Tailscale, Marimo), and S3 run in production, serving v0.2 — stood up by hand and documented step-by-step in Setting up the live service on AWS. The items further down are what remains 🚧 after v0.1.

Every piece of the AWS infrastructure above is built and running, documented step by step in Setting up the live service on AWS; the orchestration design behind the deployment is in Production Deployment — Design.

Still 🚧 after v0.1:

  • A bigger backtest task definition (e.g. 8 vCPU / 32 GB) — the live 4 vCPU / 16 GB definition exists; right-size it after a week of CloudWatch metrics.
  • Per-task failure email alerting (a failed run → SNS → email) — Sentry error telemetry and the missed-check-in alarm already shipped in #63; this is the one piece of alerting still open. Decided 2026-07-14: prefer portable alerting logic over AWS-native glue (no EventBridge rules) — the checks should be plain code that runs end-to-end on a laptop or any cloud, with only the thin notification edge (SNS, SMTP, …) being platform-specific. Under the accepted option, Dagster's own run-failure sensors are the natural portable mechanism (the daemon evaluates them); an EC2 instance-status-check alarm and the missed-check-in alarm cover the silent-failure classes ("daemon silently dead") that per-task alerts miss. The SNS-subscription-confirm step joins the runbook once this lands.
  • Infra-as-code (#326) once there's enough to justify it — per the Access phasing sequencing note, that point is Stage 2, not Stage 1. Open question, not yet decided: a small Terraform module (one file) versus AWS CDK (Python). The case for CDK is specific to this project: it's single-cloud (AWS-only), so there's no cross-cloud benefit from HCL, and CDK lets the infra be written in Python rather than learning a new language for it. Terraform vs CDK is a call for whoever starts Stage 2 work; this page does not pick one. The working assumption for after the NIA project (NGED runs the service on its own AWS account — see Handover to NGED) adds two inputs to that call: the infra-as-code must be account-portable (no OCF-specific names or network assumptions baked in), and the tools NGED's engineers already use, and the tools NGED's standards permit, matter as much as what suits OCF. Agree the choice with NGED before making it. By handover time, infra-as-code is mandatory, not optional.

The issues below are the ones still open. Everything else under the v0.1 epic (#137) has shipped, and that epic is the record of what landed when.

Issue Where it lands in this plan
#246 Scale power_fcst to [−1, +1] using the static P99 effective capacity Not detailed on this page — decided 2026-07-03 (see the issue for the full worklist); an open follow-up, not required for v0.1
#96 Write power forecasts in schema agreed with NGED Deferred to the v1.0 epic (#133) — v0.1 is "forecast running", not "delivery contract live"
#5 Backup procedure for data & models on Jack's workstation Deferred to the v0.2 epic (#138); largely superseded once S3 is the primary store

Monitoring — tests and verification

Tests:

  • Sensor fires on a power update and requests the monitoring run.
  • Monitoring rows land in Delta (append-only, correct window bounds from an injected clock) and in the production_monitoring MLflow experiment — and never touch a leaderboard run.
  • The trailing window-bounds calculation is a pure helper (injected now), unit-tested.
  • retire_experiment_job refuses when results are absent (each check independently); deletes keys when both are present; MLflow + Delta untouched either way.

Verification: trigger a power update (or the sensor manually), see trailing-24h/7d metrics appear in the production_monitoring MLflow experiment and forecast_metrics; run retire_experiment_job on a throwaway experiment and watch its partitions disappear from the Dagster UI while its MLflow runs and Delta rows remain.

NWP model upgrades — order of work

Issue: #851

  1. Run the experiment under studies/, on the fold and bootstrap machinery in packages/studies/. The recovery curve sets how many weeks of post-upgrade training count as enough, and the decision rules say whether the post-upgrade flag or recency weighting goes into the production model.
  2. Add the dated list of upgrades and the cycle column to Nwp and PowerForecast, after the contract change is agreed. The column's value at an upgrade boundary needs a test: ECMWF brings in each cycle at the 06 UTC run, so the 00 UTC run of the implementation day belongs to the old cycle.
  3. Record the cycles each training run saw, in weeks per cycle, in the model's saved config, so serving can tell when a row's cycle is short of the threshold.
  4. Decide the two options: cutting the canonical cross-validation folds by cycle, and the post-upgrade warning row and digest event. If the warning row and event are taken, they get the same guard as every other warning path: they must not be able to fail the asset they warn about.
  5. Widen the bands for post-upgrade rows, once quantile output (#263) and regime-conditional calibration exist.
  6. Add the early-retrain trigger and the change-point detector. The detector needs a test that it fires on a synthetic step at one init_time and stays quiet on a seasonal ramp.