Estimating the money a better forecast saves

Status: 🚧 Planned (v0.3). Epic: #6; issue: #606. This page is the plan for two leaderboard metrics that express forecast skill in pounds. It is written to be read by anyone numerate. Assumptions marked as open are awaiting confirmation from NGED. See the roadmap index for status conventions.

Read this first: these metrics only exist to rank ML models; they are too simplistic to be used for anything more

These metrics put a £ figure against every model we train. That figure rests on an invented network limit and a couple of average prices, so it is a rough proxy: not a cost analysis, not a business case, and not quotable as either. Its one job is to rank forecasts on the axis NGED care about, turning "this model has a lower threshold-weighted continuous ranked probability score" into "this model would have reduced costs". We use pounds rather than a unitless score because the parameters genuinely are prices, and because pounds are what the decisions these forecasts feed are actually made in. Forecast developers do not usually tune on money: Gürses-Tran and Monti (2022) observe that forecast developers "predominantly assess residuals and error statistics when tuning the targeted model's quality". As a result, "eventual cost or rewards of the underlying business application are typically not considered in the model development phase".

Two savings, measured separately

A better forecast creates value through two different mechanisms, with different prices and different beneficiaries. We compute them as two metrics, reported as two numbers, and never add them up:

  1. Flexibility procurement. NGED pay flexible customers to reduce demand when a site risks running beyond its limit. NGED procures flexibility conservatively as a safeguard against forecast uncertainty, so a sharper forecast needs less flexibility for the same security. Metric 1 measures NGED's own spend on flexibility.
  2. Curtailment of generation. Generators are curtailed to keep exports within network limits. Curtailment avoided is generation sold, priced as a whole-system cost rather than a saving to NGED or the connected generator specifically — see curtailment price basis.

A third saving — the engineer-hours freed by replacing the manual heuristic with an automated forecast — is real, but it is not a leaderboard metric: it is identical for every model we train, so it cannot rank them. This third saving belongs in the project's final report, priced in engineer-hours.

The shared idea: same risk, then compare the spend

The textbook way to price a forecast charges it for what goes wrong: £X per action taken, £Y per limit breach nobody saw coming. We cannot follow that route, because £Y — the cost of a breach — has no single figure a leaderboard can use. Pricing a breach is a business judgement rather than a property of a forecast. And in the literature that does price a forecast this way, we found no case of it being done on a real distribution network at a money-denominated cost. The energy-forecasting review reports Richardson (2000)'s cost-loss framing, Bernecker et al. (2025)'s 97% synthetic-network saving, and Angus et al. (2027)'s and Browell and Fasiolo (2021)'s capacity- and volume-denominated results.

So we invert the question. Models are aimed at equal safety, and we compare what each one spends to get there. Each model may be as conservative as it likes, and we tune that conservatism until it leaves the same small amount of risk unaddressed. Then the only thing left to compare is cost. This matches the framing the design is built on: the risk to manage is unnecessary spend, not an unaddressed breach.

The knob is the procurement quantile \(\tau\) — how far up its own forecast distribution a model looks when deciding to act. A timid model uses a high \(\tau\), buys a lot, and is rarely caught out. Calibration picks each model's \(\tau\) so that its unmet fraction — the share of genuinely-needed megawatt-hours it failed to cover — hits a common target (5% to begin with):

\[ \text{unmet fraction} = \frac{\sum_{i,t} \max(0,\; N_{i,t} - V_{i,t})}{\sum_{i,t} N_{i,t}} \]

where \(V_{i,t}\) is the volume the model would have bought (or curtailed) for time series \(i\) in half-hour \(t\), and \(N_{i,t}\) is the volume that turned out to be needed. Measuring unmet energy rather than counting missed events matters: exceedances are rare by construction, and a count of them is too noisy to rank models by.

\(\tau\) is calibrated on the training window of the leaderboard fold, never on the validation window it is scored on — otherwise a model sees its own future and every pound of the "saving" is lookahead. This has a methodological drawback: the training window is data the model was fitted to, so its residuals are smaller than they will be out of sample. As a result, \(\tau\) comes out too low, and every model under-procures on the scored window. The model that overfits hardest gains most from this.

Equal risk is therefore a target, not a guarantee, and this is the design's main weakness. What a model realises on the scored window is whatever its tail calibration delivers there. A model that overshoots the target spends less and can top the leaderboard while being materially less safe. The realised out-of-sample unmet fraction is reported beside every cost, and a cost read without it is meaningless. Two models are only comparable on cost when their realised unmet fractions are close.

What the volumes cost

Flexibility is bought in two parts, and the distinction is the whole point of these metrics. Availability is paid on every megawatt-hour held ready, whether or not it is called; utilisation is paid only on what is actually dispatched. Over-procurement therefore costs the availability price on the excess, not the far larger utilisation price:

\[ C = p_{\text{avail}} \sum_{i,t} V_{i,t} \;+\; p_{\text{util}} \sum_{i,t} \min(V_{i,t},\, N_{i,t}) \]

The second term is nearly identical for every model — it is set by what the network actually needed. So the ranking is carried by the first. Charging one blended price against all procured volume would overstate the cost of over-procurement several times over.

This formula only holds for short-term contracts, tendered day-ahead against a forecast. NGED also buy long-term contracts, whose availability is tendered roughly a year ahead of delivery, independent of any forecast we produce now. A better forecast cannot reduce that volume, because it is already committed by the time our forecast exists. Only the utilisation decision on long-term-covered volume — whether to call on capacity already secured, decided day-ahead (up to 5 days ahead around a weekend or bank holiday) — is forecast-sensitive. Metric 1 therefore has two components, scored separately per (time_series_id, direction):

  • Long-term-covered volume: only the utilisation term is scored against \(N\). Availability spend is fixed regardless of forecast and is excluded from the metric.
  • Short-term volume: the full formula above applies unchanged.

Both prices, for both contract types, are configuration: we compute a volume-weighted average price per contract type from National Grid's published flexibility-trades data (see implementation details) rather than hardcoding a placeholder, and NGED's own rates can replace that computed price without a retrain once confirmed — see questions for NGED.

Metric 1 — flexibility procurement cost

For time series \(i\) and half-hour \(t\), with demand-side limit \(L_i\):

Quantity Definition
Volume procured \(V_{i,t} = \max(0,\; \hat q_{i,t}(\tau) - L_i) \times 0.5\) MWh
Volume needed \(N_{i,t} = \max(0,\; y_{i,t} - L_i) \times 0.5\) MWh

\(\hat q_{i,t}(\tau)\) is the model's \(\tau\)-quantile forecast, \(y_{i,t}\) the observed power, and \(\times 0.5\) converts MW held for a half-hour into MWh. For a half-hour covered by a long-term contract, \(V_{i,t}\) and \(N_{i,t}\) are unchanged but only the utilisation term \(p_{\text{util}} \min(V_{i,t}, N_{i,t})\) is charged.

Worked example. A substation whose limit sits at 30 MW, on one winter evening half-hour, with short-term availability at £75/MWh and utilisation at £750/MWh (both placeholders, pending real volume-weighted prices). Forecast A (more conservative) says 33 MW, so it procures \((33 - 30) \times 0.5 = 1.5\) MWh. Demand turns out to be 30.6 MW, so 0.3 MWh was needed. Forecast A pays £112.50 availability and £225 utilisation. Forecast B says 31.0 MW, so it procures 0.5 MWh and pays £37.50 availability and the same £225 utilisation — £75 less than Forecast A. If the same half-hour were instead covered by a long-term contract, both forecasts pay only the utilisation term (£225 each) and Forecast B saves nothing on that half-hour. The metric sums this over every half-hour and every series, split by which contract type covered each half-hour.

Metric 2 — curtailment cost

Curtailment is not decided per meter: a generation constraint typically binds above the primary, driven by the aggregated flow across several substations rather than by any single meter in isolation. Scoring each time_series_id independently, as Metric 1 does for flexibility, would misrepresent how curtailment actually gets triggered. We instead define three tiers of increasing realism, each documented separately with its own scope and caveats, all keeping the "these numbers rank models, they do not cost anything" disclaimer above — none is a validated £-saved figure without a real case study behind it.

Tier 1 — per-primary netting

At one primary, net the local generation forecasts against the local demand forecasts before comparing the result to the primary's export limit, instead of scoring each meter independently. Otherwise identical to the Metric 1 arithmetic, with the export-side limit and the curtailment price \(p_{\text{curt}}\) (£/MWh of network access) charged against total volume curtailed, since curtailed generation is lost whether or not the constraint was real. There is no hierarchy in this tier: each primary is scored in isolation.

Worked example. A generation-dominated feeder with an export limit of 8.5 MW. The netted forecast at its calibrated quantile says 9.6 MW, so 0.55 MWh is curtailed; actual net export is 8.7 MW, so 0.1 MWh needed curtailing. At £100/MWh that is £55 against £10 of real constraint — £45 of generation curtailed for nothing.

Caveat. This tier is only valid where a primary's export is electrically isolated from its neighbours. Where primaries share a constraint — operate "in parallel" — curtailment must be assessed jointly across the group, not per primary. Which primaries in the trial area operate in parallel is an open per-site question, not a question this tier can assume away. Treating every primary as isolated will overstate how much curtailment Tier 1 avoids at any site that actually shares a constraint.

Tier 2 — substation hierarchy, no power-flow

Sum active-power forecasts (generation minus demand) up the known substation hierarchy, one node at a time, and compare each node's summed forecast against a limit for that node. This is Tier 1 with the netting extended from one primary to every node above it.

The limit at each node is a synthetic toy limit: the same historical_p99-style percentile-of-history device already used per series (see choosing the limit), applied at the node level instead — the percentile of that node's own historical summed power. Where NGED supply a real rating for a node, we use that instead.

Caveats.

  • No reactive power, voltage drop, or N-1 contingency modelling. A hierarchy sum of active power is not a load-flow study; Tier 3 is where that modelling belongs.
  • Coverage gap. Only some of a node's children have a forecast in the trial area; the rest need a metered-actuals or historical-baseline stand-in, which adds a second error source on top of forecast error at every node above the trial-area leaves. This gap shrinks as trial coverage scales towards the ~2,500-series v2 rollout — it is a limitation of the trial's current coverage, not a fixed limitation of the tier.

Tier 3 — full power-flow modelling

Out of scope for Flexpectation, including v2. Tier 3 is documented as the eventual correct approach — modelling reactive power, voltage drop, and N-1 contingencies explicitly — but it is gated on power-flow integration work that sits outside this project.

Tier 3 is also where a real curtailment case study becomes possible. Tiers 1 and 2 can each be computed and can rank models without Tier 3. What they cannot yet do is be validated against a real curtailment event, because no existing site maps a curtailment case to a specific series or a single hierarchy node — see case studies below.

NGED derives upstream limits by combining substation forecasts in a power-flow model, so the forecasts must stay consistent across substations. Percentiles cannot be added across substations: the sum of each substation's 95th percentile is generally not the 95th percentile of the combined flow. An ensemble member describes one weather outcome at every substation at once, so ensemble members can be fed through a power-flow model member by member. The power-flow model is therefore a reason to keep delivering the ensemble of deterministic forecasts alongside the percentile representations.

Tier 3 is not gated on the speed of the power-flow solve. Nguyen et al. (2026) train a self-supervised surrogate for multiphase alternating-current (AC) optimal power flow. That is the dispatch optimisation layered on top of a power-flow solve, and Tier 3 needs only the solve. The surrogate still shows how fast the harder of the two problems can run. On feasible, in-distribution test cases it stays within 0.2% of the cost the interior-point solver IPOPT reaches. It runs one to three orders of magnitude faster than IPOPT, reaching 780 and 1,121 times on the two largest IEEE test feeders it was tried on, which range from 13 to 8,500 nodes. That comparison times batched inference on a graphics processing unit against IPOPT on a central processing unit. Nguyen et al. do not time the power-flow solve separately from the optimisation. Their results give no reason to think the solve is too slow to push an ensemble through member by member.

NGED already publishes an electricity-network model, so the gate is integration work rather than a missing model. Nguyen et al.'s method needs three inputs: per-branch impedances, per-branch thermal ratings, and voltage limits. NGED publishes the impedances and the thermal ratings as open data, in its Long Term Development Statement. See data sources for what the two publications contain. Joining either publication to the time_series_ids Flexpectation forecasts is unscoped work.

Fractal Flow, a Northern Powergrid project building a shared cross-operator digital twin, is not a route to that model. The twin is wider in scope than Tier 3 needs, and arrives later. The project's Strategic Innovation Fund Beta registration describes a shared, near-real-time digital twin across the transmission-distribution boundary. Every GB distribution system operator (NGED included) and the National Energy System Operator (NESO) are Beta partners. The Beta phase runs from September 2026 to September 2028. That phase trials the twin on historic data in three control rooms, none of them NGED's. The registration puts phased rollout at 2030, extending to all distribution system operators by 2035.

Fractal Flow also sits on the far side of the forecasting boundary from Flexpectation. The registration describes the twin combining distribution network operator ("DNO") and NESO forecasts "into a unified view up to 24-hours ahead of the settlement period". Separately, the registration describes the twin predicting "possible power-flow changes through the network 24-hours ahead of the settlement period".

Curtailment price basis

£100/MWh is a whole-system cost: the cost to all electricity users from re-dispatching generation up the merit order to relieve the constraint, not a cost borne specifically by NGED as network operator or by the curtailed generator. This is the basis Metric 2 is priced on throughout. It may change: the network operator could in future need to pay a flexibility counterfactual cost to curtail generators directly, at which point curtailment would carry a network-operator-borne price alongside the whole-system one.

A published annual curtailment-saving figure may use a capacity-based method, in which case the published figure is not directly comparable with this metric. This metric prices MWh curtailed, whereas a capacity-based method starts from MW of capacity and scales it for export volume. A comparison between the two figures needs either a separate replication of the capacity-based method or a label saying the comparison is order-of-magnitude only.

Which direction is the constraint on?

There is no single sign rule — see sign convention. The trial area contains both conventions, plus battery sites that both charge and discharge. Constraint-side direction is therefore resolved per time_series_type, reusing the mapping the tail and exceedance metrics already need, with the ambiguous types to be confirmed with NGED.

A series constrained in both directions gets a limit in each, so the threshold is one scalar per (time_series_id, direction) rather than per series alone. Each metric is computed only where its direction is constrained: a demand primary with no connected generation gets no curtailment cost, and a solar meter gets no flexibility procurement cost. Applying one global rule instead would silently score £0 for every generator meter in the trial area.

What each number is compared against

Every model's cost is reported beside two reference points, computed on the same series and half-hours:

  • Manual heuristic — the 13-analogue ensemble, summarised at one percentile if a single number is needed (the manual heuristic forecast). That percentile is an upper percentile chosen to match the company's risk appetite; our scoring uses the 95th percentile. The residual-risk level the operating point is set to is still an open question. The manual heuristic is scored at that actual operating point, not calibrated to the common risk target, because the point is to measure the manual heuristic as it is operated. Its realised unmet fraction is therefore an output — the number saying what risk level the manual heuristic works to — and the saving against it mixes a change in spend with a change in risk. Both are reported; neither means much alone.
  • Perfect forecast — the least that can be spent while leaving no more than the target fraction \(u\) unmet. Truth is not a distribution, so there is no quantile to calibrate: the floor is the cost of procuring exactly \((1-u)N_{i,t}\) in every half-hour, put straight through the same price formula. Setting it at zero unmet instead would put it above a model calibrated to 5%, and models would routinely score over 100% of the available saving.

The headline is "£X less than the manual heuristic, which is Y% of the £Z a perfect forecast would save", always alongside the realised unmet fractions. Note that a model whose realised unmet fraction overshoots the target can still exceed 100%; that is a signal to read the risk column, not a bug.

Choosing the limit

Real network limits move with ambient temperature, with how long an overload lasts, with season and with switching state, so no single number is correct — the fuller version of this caveat is in the threshold-choice discussion. We use a synthetic limit: the 99th percentile of each series' own full observation history, in the constrained direction, labelled historical_p99 to keep it distinct from the forecast-quantile label p99 — one is a fixed power level derived from history, the other a level of the forecast distribution.

This mirrors a percentile-of-history convention already used for capacity setting, treating winter as close to the limit throughout, and it is the same single rung the tail and exceedance metrics use, so the leaderboard carries one threshold concept rather than several. The percentile sets the absolute size of every £ figure on this page — a lower rung would multiply them — which is another reason to read these numbers as a ranking instrument rather than a total.

historical_p99 is a closer proxy to a real network rating than an arbitrary percentile would be: this is methodologically consistent with how comparable network ratings are typically derived, so the synthetic limit is close to the practice it stands in for, not just a convenient round number.

Where NGED supply a real firm or flex rating we will compute the same metrics against it, as a case study. A rating never breached during the scored window is not useless here — procurement volume is driven by the forecast crossing the limit, so models still rank — but the unmet fraction goes undefined, and ratings are not available for every series and sit at different points of each series' distribution, so they cannot carry the cross-series leaderboard.

Case studies

  • Flexibility procurement (Metric 1) — Tavistock Primary, CMZ_T9A_SWE_0050, South West. Buildable now. Tavistock has winter demand that reaches the level at which the zone procures flexibility, a seasonal transformer rating (13 MVA in winter, 10 MVA in the intermediate-cool, intermediate-warm, and summer periods — treated as MW, assuming negligible reactive power at this transformer), and real procurement history, all from public sources. "Winter" here is whatever calendar period NGED's own rating table uses, not a fixed date range; the exact month boundaries need confirming against the dataset rather than assumed. Procurement history for Tavistock specifically is in National Grid's flexibility trades data and results dataset; the same dataset's long-term contracts resource (excluding any CMZ with "LV" in its name) and short-term contracts resource, across all zones, feed the volume-weighted average prices in what the volumes cost.

  • The curtailment case study is blocked, not the curtailment metric. Tiers 1 and 2 need nothing that does not already exist, so each can rank models as soon as it is implemented. Tier 2 does not wait on Tier 3. What is blocked is validating either tier against a real curtailment event: mapping such an event to a specific series or hierarchy node needs Tier 3 power-flow modelling — see Tier 3. The trial area has two nominal flexibility zones with an export-side constraint, but neither has enough dispatch history to stand in as a case study.

What these numbers do not capture

  • The limit is invented, and fitted on the scored window. A percentile of history is not a network rating, and it is computed over the full history including the months being scored. It is model-independent, so it cannot favour one entrant, but it is not an out-of-sample quantity.
  • The history is already post-intervention. At a genuinely constrained site the metered power reflects flexibility that was dispatched and generation that was curtailed. So \(N\) understates true need, and the percentile limit derived from that same history is itself shaped by the interventions we are pricing.
  • Ten trial-area sites cannot see direction at all. They are metered in MVA, which reports the magnitude of flow, so reverse power flow appears as a rise rather than a sign change (see data quality). At those sites an export event would be billed as demand-side procurement, and multiplying MVA by half an hour gives MVAh, which is not the megawatt-hour a flexibility price is quoted against.
  • Unmet energy is pooled across series and half-hours. A model can hit the 5% target by covering the largest site well and abandoning many small ones, and 5% concentrated in one deep breach is far worse operationally than the same 5% spread thinly. Harm grows faster than depth; equalising energy does not equalise harm. The per-series distribution of unmet energy is reported for this reason.
  • The prices are single averages. Two numbers stand in for a tendered market with zone-by-zone clearing prices and finite liquidity.
  • Procurement is not per-half-hour. NGED tender flexibility ahead, in blocks and windows. Our arithmetic assumes perfectly granular buying, which flatters every model equally but overstates the achievable saving.
  • Ensemble size limits how finely \(\tau\) can be tuned. The manual heuristic has 13 analogues, so its quantiles come in coarse steps; a 51-member ensemble is far finer. Models of different ensemble size cannot be landed on exactly the same risk.
  • Costs are per fold, and folds are seasonal. The limit concentrates exceedances at winter peak, so annualising a fold that does not span a whole year is meaningless, and a fold with no exceedance leaves the unmet fraction undefined.
  • Nothing is validated against real spend, except the Tavistock flex-procurement case study. The curtailment metric has no equivalent validation yet, and cannot until Tier 3 exists.
  • Asset failure and outage costs are excluded. Outage quantification is valuable but harder, and is not in this design.
  • Some procurement does not depend on the forecast. Procurement that serves wider aims, such as developing the flexibility market and supporting the capital programme, does not depend on the forecast. A better forecast should not be credited with removing that procurement.

Questions for NGED

Resolved:

  • Flexibility prices, split by contract type — rather than asking NGED for a single availability and utilisation rate, we compute volume-weighted average prices separately for long-term and short-term contracts from National Grid's published flexibility-trades data; see what the volumes cost.
  • Curtailment price basis and who bears it — £100/MWh is a whole-system cost, not one borne specifically by NGED or by the curtailed generator; see curtailment price basis.
  • Case-study data availability — Tavistock Primary (CMZ_T9A_SWE_0050) has real procurement history and a seasonal transformer rating, and anchors the flexibility-procurement metric against a real site; see case studies.
  • Whether curtailment can be validated against a real event today — no, not below Tier 3.

Still open:

  1. Is the 95th percentile of the 13 analogues the operating point the manual heuristic is operated at? What residual-risk level is the operating point set to?

Cost-benefit analysis in the final work package

NGED will run their own cost-benefit analysis in the project's final work package, and the choice of method is theirs. The final work package is tracked as WP7, due February 2028.

One method worth recommending to NGED is a relative-economic-value curve in the shape of Richardson (2000), computed per substation, across the range of ratios between the cost of acting on a forecast and the loss avoided by acting. The shared idea above explains why this page took a different route: £Y, the loss avoided by a breach, has no single figure the leaderboard metrics can use. NGED's own final work package is better placed to supply that figure, because pricing a breach is a business judgement rather than a property of a forecast.

Implementation details (deleted when this ships)

  • Two functions in packages/ml_core/src/ml_core/metrics.py, sharing a private helper taking the limit, the prices and the direction. They consume the same ensemble-member rows as the existing quantile metrics.
  • This needs a Metrics contract change, still to be reviewed and agreed when we implement: METRIC_NAMES gains flex_procurement_cost_gbp, curtailment_cost_gbp and unmet_fraction, and METRIC_PARAMS gains a historical_p99 label per constrained direction. Bare "p99" already exists in QUANTILE_METRIC_PARAMS meaning a forecast quantile, so a history-derived power level has to stay distinct from a level of the forecast distribution.
  • Two things the design needs to store have nowhere to live in Metrics today: the number of half-hours a cost row covers (without it, totals cannot be compared across folds of unequal length) and the calibrated \(\tau\) (which says how conservative a model had to be to reach the common risk target, and is interpretable on its own). Both need resolving with the contract change.
  • Costs are stored per time_series_id, summed over time only, so they fit the existing primary key. Only \(\tau\) and the unmet target are pooled across series. Curtailment Tiers 1 and 2 net across series before pricing, so their cost belongs to a primary or hierarchy node, not a single time_series_id — this needs its own key, still to be resolved with the contract change.
  • Flexibility-price computation is a data pipeline task, not hardcoded: pull National Grid's published flexibility-trades resources (see case studies), split by contract type, and compute a volume-weighted average price per type. This price-computation step has no home in the codebase yet.
  • _log_metrics_to_mlflow aggregates with mean(), which is right for every metric that exists today and wrong for these: the portfolio headline is a sum over series, and pooled unmet_fraction is \(\sum N\)-weighted, not an unweighted mean that a tiny site can dominate. The MLflow aggregation needs a per-metric rule before these land.
  • Prices, the risk target and the limit percentile are configuration, not constants in code, so NGED's answers can be applied without a retrain.
  • Scored on a single lead-time slice (day_ahead until we know when the procurement decision is actually made) rather than all horizons pooled.